Contractor in liquidation: how to regain control of the site

Contract, work in place, payments and restart: the decisions to organise when a contractor is placed in judicial liquidation in France.

Read the guide 14 min read

By Alain Bonnetaud, founder of PRIMOE · Updated · published

The judicial liquidation of a contractor immediately confronts the client with several urgent issues: protecting the building, knowing the actual progress, understanding what will become of the contract and regaining the capacity to build. These matters move forward together. Waiting for a new firm before establishing the state of the site loses time and evidence.

For a private project, the method is to build a restart file shared between the client, its lead consultant and its advisers, so that decisions can be made on verifiable facts while respecting the insolvency proceedings. It is the first step in a stalled site recovery. This guide describes the method on the site side; the procedural steps are prepared with your lawyer.

What should you do when a contractor on your site is in judicial liquidation?

Six steps run in parallel: obtain the judgment and the liquidator’s name, make the site safe, have progress formally recorded, serve formal notice on the liquidator to decide on the contract, lodge your claims, and notify insurers and subcontractors. The statutory time limits run from publication of the judgment in the French official gazette of civil and commercial notices (Bulletin officiel des annonces civiles et commerciales, BODACC).

  1. Confirm the proceedings. Obtain the opening judgment or the notice published on bodacc.fr. Note the date of publication, the name of the liquidator and the court: safeguard, reorganisation and liquidation proceedings do not call for the same steps.
  2. Make the site safe. Access closed off, work protected from water ingress, collective safety protection checked. Each intervention is limited, dated and recorded.
  3. Have progress formally recorded. Call a joint inspection, area by area, inviting the liquidator.
  4. Serve formal notice on the liquidator to take a position on whether the contract will continue, by recorded delivery with acknowledgement of receipt. It is this letter that starts the one-month period.
  5. Lodge your claims with the liquidator: overpayments, penalties, estimated extra cost of completion.
  6. Notify your insurers and list the subcontractors. Suspend any payment whose recipient or amount has not been checked.

Scroll the table sideways →

StepTime limit set by lawLegal text
Liquidator’s reply to the formal notice to take a position on the contractMore than one month without a reply: automatic termination. The supervising judge may set a shorter time limit or grant an extension of up to two months.Commercial Code, Article L641-11-1, III, 1°
Proof of claims arising before the judgmentTwo months from publication of the judgment in the BODACCCommercial Code, Articles L641-3 and R622-24
Proof of the claim arising from termination of the contractOne month from automatic termination or from notification of the decision ordering itCommercial Code, Articles R622-21 and R641-25
Application for relief from the time bar, if the deadline for lodging claims has passedSix months from publication of the judgment, subject to conditionsCommercial Code, Article L622-26
Claim to materials by a supplier that has retained ownershipThree months following publication of the judgmentCommercial Code, Article L624-9
Direct claim by a subcontractor against the clientAvailable if the main contractor has not paid one month after being given formal noticeLaw No. 75-1334 of 31 December 1975, Article 12

In short: confirm the proceedings, protect the site, have progress formally recorded, then write to the liquidator. Two deadlines matter above all: one month for the liquidator’s reply to your formal notice, and two months after publication in the BODACC to lodge your claims.

Does judicial liquidation end the works contract?

No. Under French law, the opening of judicial liquidation does not, in itself, end a contract in progress: Article L641-11-1 of the Commercial Code expressly rules this out, whatever the contract clause says. The contract ends if the liquidator declines to continue it, if the liquidator leaves your formal notice unanswered for more than a month, or if the supervising judge (juge-commissaire) orders termination.

A contract clause providing for automatic termination in the event of insolvency proceedings is therefore not enough: the text applies “notwithstanding any statutory provision or contractual clause”. Before writing to the contractor or giving the trade package to another, have the status of the contract checked.

Only the liquidator has the power to require performance of contracts in progress. The other party may serve formal notice on the liquidator to decide. If that formal notice remains unanswered for more than a month, the contract is terminated automatically; before that period expires, the supervising judge may shorten it or grant an extension of up to two months (Article L641-11-1, III, 1°). The addressee, the content and the date of receipt of the letter must therefore be secured.

Once the period has elapsed, any interested party may ask the supervising judge to record the automatic termination and its date (Article R641-21 of the Commercial Code). This order gives the end of the contract a date that cannot be disputed, which is useful for the new contract, the insurers and the proof of claim. If the liquidator does not continue the contract, the non-performance may give rise to damages, the amount of which is lodged as a claim against the estate (Article L641-11-1, V).

This legal step is separate from making the site safe. Urgent protection may be needed without waiting for the outcome on the contract; it must not remove anything useful for recording the existing work.

In short: the contract survives the liquidation judgment. It ends by the liquidator’s decision, by the liquidator’s silence for more than a month after a formal notice, or by an order of the supervising judge. Until that point is settled, only protective measures are justified on the work in the trade package.

How do you draw up a usable progress record?

A usable progress record describes, area by area, what is finished, what is started, what is defective and what has only been delivered to site. It is drawn up jointly, with the liquidator invited, and is backed by dated photographs showing their location. An overall percentage is not enough to settle the accounts or to run a tender.

A trade package said to be almost finished may include completed work, materials not yet installed, defective work and tests never carried out. Each category weighs differently on the restart price and on liability. The minutes of the visit state who was present, who was absent, the documents consulted and the areas that could not be accessed. Photographs, linked to the observations, keep the file usable several months later.

Scroll the table sideways →

Item to recordDocument to keepUse for the restart
Work carried out, by areaSurveys, quantities and photographsDefine what really remains to be built
Defects and incomplete workDefect sheets with locations, and test resultsSeparate completion, repair and investigations
Materials and equipmentInventory, invoices and hire contractsCheck who has rights over them before any use
Design work and documentsDrawings, revisions, approvals and calculation notesRebuild the available technical file
Access and temporary installationsStatus of keys, supplies and protectionOrganise the safekeeping of the site

A judicial officer’s report (constat de commissaire de justice) can complete the file when the evidential stakes justify it. It replaces neither the technical analysis of the work nor the investigations needed to understand a defect. Our guide Site audit: how to get a diagnosis you can act on explains how to carry out this assessment and report on it.

In short: the progress record separates what is finished, unfinished, defective and delivered to site, trade package by trade package and area by area. Drawn up jointly, it underpins three things at once: the account with the insolvency proceedings, the proof of claim and the tender file for the contractor who will take over.

Can you use the materials left on site?

Not without checking. Materials on site do not automatically become available to the client: they may belong to an unpaid supplier, be subject to a retention of title clause or be hired. Until their ownership is established, they are inventoried, protected and left in place.

Under French law, a seller holding a written retention of title clause may claim goods that are still identifiable in kind, within three months following publication of the judgment (Articles L624-16 and L624-9 of the Commercial Code). The inventory therefore distinguishes physical presence from the right to use the goods.

At the same time, the lead consultant identifies the protective measures: closing off access, preventing water ingress, checking collective safety protection, organising security and preserving sensitive work. For propping, electrical installations or unstable structures, intervention by a competent contractor or specialist must be arranged.

The inventory matches each delivery to its invoice, its delivery note and the valuations already paid. The liquidator is asked in writing before any use.

How do you rebuild the accounts and lodge your claims?

The accounts are rebuilt by reconciling the contract, the amendments, the recorded progress, the valuations invoiced and the payments. Any balance in the client’s favour is lodged with the liquidator within two months of publication of the judgment in the BODACC. After that deadline, the claim is excluded from distributions, unless relief from the time bar is granted.

In this financial schedule, discrepancies must remain visible: an advance not yet recovered, deliveries not supported by documents, work invoiced but unfinished, or extra spending to be expected. The method for checking valuations is described in our guide Payment certificates: what to check on a private contract.

The two-month deadline comes from Articles L641-3 and R622-24 of the Commercial Code. A claim whose amount is not yet fixed is lodged on the basis of an estimate (Article L622-24): this is the case for the extra cost of completion until the restart contract is signed.

Two further deadlines complete this rule. The claim arising from termination of the contract is lodged within one month of the automatic termination or of notification of the decision ordering it (Article R622-21, made applicable to liquidation by Article R641-25). A creditor that has missed the deadline may ask the supervising judge for relief from the time bar (relevé de forclusion), within six months of publication of the judgment, if it shows that its failure was not its own doing (Article L622-26).

Subcontractors need to be followed up separately. Who they are, whether they were accepted and any claims in progress can affect payments. Under French law, a direct claim against the client may be brought under certain conditions, including in liquidation; its basis depends on the sums still owed to the main contractor when the client receives a copy of the formal notice (Articles 12 and 13 of Law No. 75-1334 of 31 December 1975). Any planned payment must take this into account.

In short: a single schedule links contract, amendments, recorded progress, valuations and payments. It is used to lodge the claim within two months of publication in the BODACC, on an estimated basis if the amount is not settled, and to avoid paying anything that a subcontractor could claim a second time.

Which insurance and guarantees can still be called on?

Liquidation does not make the guarantees attached to the contract disappear: retention or guarantee, the contractor’s ten-year latent defects liability insurance, and the client’s building damage insurance (dommages-ouvrage). None of them, on its own, funds completion of the site. Each is called on under its own conditions, to be checked contract by contract from the first days.

  • The retention. Under French law, on a private works contract, interim payments may be reduced by a retention of no more than 5%, provided for in the contract, which secures performance of the works and the clearing of the snags. It does not apply if the contractor has provided a guarantee from a financial institution (Article 1 of Law No. 71-584 of 16 July 1971). Check which of the two exists, and with whom.
  • Ten-year latent defects liability insurance. In France, any contractor that may incur ten-year liability (décennale) must be insured, and the policy is deemed to maintain cover for the whole duration of that liability (Article L241-1 of the Insurance Code). The cover applies to damage that compromises the structural soundness of the building or makes it unfit for its purpose (Article 1792 of the Civil Code), for ten years from practical completion (Article 1792-4-1 of the Civil Code), not to the cost of completing an interrupted site.
  • Direct claim against the insurer. The injured third party may bring a claim directly against the contractor’s liability insurer (Article L124-3 of the Insurance Code). Hence the importance of keeping the insurance certificates provided when the contract was signed.
  • Building damage insurance (dommages-ouvrage). Before practical completion, it guarantees payment for the necessary repairs where, after a formal notice that has remained unheeded, the contract is terminated for non-performance by the contractor of its obligations (Article L242-1 of the Insurance Code). It covers damage of a ten-year latent defects nature, not the work still to be done.

Insurers are informed of the situation according to the policies concerned. The one-year defects warranty, owed by the contractor for one year from practical completion (Article 1792-6 of the Civil Code), assumes a contractor able to do the work: in practice, the retention or the guarantee takes its place.

In short: reread four documents as soon as the liquidation is announced: the retention clause or the guarantee deed, the contractor’s ten-year liability insurance certificate, your building damage insurance policy and the notifications already made. The extra cost of completion, for its part, remains a claim to be lodged against the estate.

How do you tender the restart to a new contractor?

The restart tender relies on a file that separates four kinds of work: work kept as it is, preliminary investigations, repairs, and new work still to be done. Bidders visit the site, consult the design documents and put in writing their reservations about the existing work. Without this, prices are not comparable.

The future contract sets out the scope boundaries, the tests expected, the documents to be revised and the insurance conditions. A contractor does not automatically take on all of its predecessor’s liabilities; its commitments on the existing work, and on the work it covers or alters, must be examined explicitly.

The restart schedule starts from the real prerequisites: availability of the file, legal release of the contract, surveys, orders, approvals and getting temporary installations back into service. A date announced without these dependencies can recreate the same blockage in the first week. How to build this schedule is explained in our guide Stalled site: how to build a recovery plan that holds. The days lost before and after the judgment are tracked separately: see Construction delays: how to prove them and apply penalties.

A contractor liquidated during the works: your questions

Can the client replace a contractor in judicial liquidation straight away?

Not before the fate of the contract has been clarified. Under French law, the judgment does not terminate the contract: the liquidator must decline to continue it, stay silent for more than a month after a formal notice, or the supervising judge must decide. Urgent protection of the site is organised separately, through limited and documented interventions.

How long does the liquidator have to say whether it will continue the contract?

The French Commercial Code sets no time limit as long as no one asks. It is the other party’s formal notice that opens a one-month period, at the end of which silence amounts to automatic termination. The supervising judge may shorten it or extend it by up to two months (Article L641-11-1 of the Commercial Code).

What happens to advance payments made for work not carried out?

They are a claim against the contractor, to be lodged with the liquidator within two months of publication of the judgment in the BODACC. Lodging the claim does not guarantee repayment: that depends on the assets in the proceedings and on the ranking of creditors. The retention or the guarantee, if the contract provides for one, is checked in parallel.

Can materials already paid for be used?

Payment is useful evidence, but it is not always enough to establish an immediate right to use them. The contract, the delivery, the invoices and any retention of title clauses held by suppliers must be checked against each other. Under French law, a supplier that has retained ownership has three months after publication of the judgment to claim its goods.

Does the ten-year latent defects liability still apply if the contractor has gone?

Yes, for the work it carried out and that has been accepted at practical completion: in France, ten-year latent defects liability insurance is compulsory and the policy is deemed to maintain cover for the whole duration of that liability. The client can bring a claim directly against the insurer. You still need to hold the insurance certificate valid when work started on site.

How long does it take to restart?

There is no standard duration. The timing depends on four prerequisites: the legal end of the contract, the joint progress record, the update of the technical file and the tender for the restart contractor. The schedule is built from these steps, with the supply lead times specific to the trade package concerned.

Who can prepare the restart file with you?

The restart file is prepared by three parties: the lawyer handles the procedural steps, the client decides, and a construction supervision (MOEX) firm records progress, rebuilds the technical accounts, prepares the tender and resets the schedule.

PRIMOE works in Paris and Île-de-France on this analysis of the works and on organising the restart, in coordination with the advisers handling the proceedings: see our stalled site recovery service and all our construction delivery services. We are providing construction supervision (MOEX, maîtrise d’œuvre d’exécution) for housing in Pantin (93), in progress, and provided it in Roissy-en-Brie (77), a completed project. A conversation based on the contracts, the latest schedule and the interim valuations helps set the priorities: contact@primoe.fr.

Example: in Pantin, PRIMOE restarted a site of 15 homes and a shop in 2026 after the main contractor failed, under a construction supervision (MOEX) and scheduling and coordination (OPC) appointment.

Alain BonnetaudFounder of PRIMOE

Contact

Let’s talk about your project.

A building to study, a construction site to run or restart, an operator to find: tell us where you stand.

3 rue Alfred Roll, 75017 Paris, France · Projects across Paris and Île-de-France

Or describe your project in a few lines.

Your details are used only to reply to you. They are never passed on or used for marketing. Your data (in French)