Construction supervision (MOEX, maîtrise d’œuvre d’exécution) runs the construction phase of a project: it ensures the works comply with the drawings, the contracts and good building practice. PRIMOE handles the approval of construction drawings, site management, practical completion and clearing the snags, in Paris and Île-de-France, with three sites at most per project manager and written site minutes as standard. At PRIMOE, a MOEX-only appointment costs between 3 and 5% of the cost of the works excl. VAT (our fees).

Let’s talk about your site +33 1 72 68 22 71

By Alain Bonnetaud, founder of PRIMOE · Updated

Street elevation of the Pantin housing project: a white building with loggias, set between two existing buildings
Pantin (93) · HousingConstruction supervision · in progress

What sets us apart: a commitment to results, not a token presence.

We direct the construction of your project: approval of construction drawings, site management, site minutes, practical completion and clearing the snags.

Each PRIMOE project manager runs three sites at most.

This rule means real presence on your project and decisions taken on site, not from an office.

Everything is in writing.

Site minutes, decisions, contractors’ commitments: in a sector that has long relied on the spoken word, this discipline in record-keeping prevents disputes and protects the client. Our own project management software records every decision.

  • 3 to 5%of the cost of the works excl. VAT, MOEX only
  • 15 yearsin construction
  • Île-de-Francewhere our team is based

Want to know who would run your site?

Let’s talk about your site +33 1 72 68 22 71

What is construction supervision (MOEX)?

Terms used on this page

Client
The party who commissions the works and pays for them: you.
Approval
The written review of contractors’ drawings and calculations before work is carried out.
Interim valuation
A contractor’s application for payment.
Snags
What remains to be put right or finished at practical completion.
DOE
The as-built file, handed over at the end of the works.

Construction supervision runs the construction phase of a real estate project. Where the architect designs the project, MOEX makes sure it is built in line with the drawings, the contracts signed with the contractors and good building practice, within the committed timescales and budgets.

It acts for the client, meaning you: the party who commissions the works and pays for them. It is one of the services of PRIMOE Delivery, alongside owner’s representation (AMO) and scheduling and coordination (OPC).

PRIMOE’s founder, Alain Bonnetaud, has worked in construction for fifteen years, for developers, private investors and institutional clients, on multi-unit housing, refurbishment and mixed-use projects.

How a MOEX appointment runs, step by step

A MOEX appointment starts before work begins on site, with site preparation, and ends after practical completion, once the snags are cleared and the as-built file is handed over. In between, it approves the contractors’ drawings, directs the performance of the works contracts and checks what is paid.

Before work starts on site

  1. Site preparation

    Contract review, checks on insurance certificates and declared subcontractors, site set-up, schedule for submitting construction drawings.

During the works

  1. Approval of construction drawings

    Contractors’ drawings and calculations are reviewed against the design and the contracts, then approved with written comments. No element should be built from a document that has not been approved.

    What you getThe approvals register

  2. Directing the works

    Site visits, checks on compliance with the drawings, the contracts and good building practice, written requests for remedial work, assessment of variations before they are carried out.

    What you getLetters sent to contractors

  3. Meetings and site minutes

    Regular site meetings, with minutes circulated to all parties, setting out decisions, who is responsible and deadlines.

    What you getThe site minutes

  4. Valuations and payments

    Checking the progress and quantities claimed by contractors in their interim valuations, that is, their applications for payment; recommending payment to the client.

    What you getPayment recommendations

At practical completion, and after

  1. Pre-completion inspection (OPR)

    Inspection of the works, trade package by trade package, snag list (what remains to be put right or finished), checks on the required tests and inspections.

    What you getInspection reports and snag lists for each trade package

  2. Completion, snags and as-built file

    Assisting the client at practical completion, following each snag until it is confirmed as cleared, collecting and checking the as-built file (DOE).

    What you getThe draft practical completion certificate, the snag tracker and the checked as-built file

Three legal texts frame this process.

The French Public Procurement Code, which applies to public clients, sets out the elements of a design and supervision appointment (Article R2431-1 of the Public Procurement Code): approval of construction drawings, direction of the works contracts, assistance at handover. This vocabulary is also used as a reference on private contracts; it is the consultant’s appointment that sets what is actually entrusted.

Under French law, throughout the contract, the contractor must have each subcontractor accepted, and its payment terms approved, by the client (Article 3 of Law No. 75-1334 of 31 December 1975). MOEX checks that the firms working on site match those that have been declared.

Practical completion (réception) is the act by which the client declares that it accepts the works, with or without snags; it is declared in the presence of both parties (Article 1792-6 of the Civil Code). It starts the one-year defects warranty: for one year, the contractor must remedy the defects noted in the practical completion certificate or notified in writing afterwards. To go further, see our guides on organising the approval of construction drawings and on checking interim valuations and the payment certificate.

What deliverables do you receive?

You receive written, dated and circulated documents that let you follow the site without being there and trace who decided what. The exact list is set in the consultant’s appointment; a MOEX appointment usually produces the following.

Documents handed to the client during a construction supervision appointment
What you getWhat the document containsAt which step
Approvals register Every construction document, its revision, its status and the comments made Drawing approval (step 2)
Letters sent to contractors Including formal notices where needed Directing the works (step 3)
Site minutes Progress, decisions, actions with the person responsible and the deadline Meetings (step 4)
Payment recommendations Based on the contractors’ interim valuations, with the status of variations Payments (step 5)
Pre-completion inspection reports With snag lists for each trade package Before completion (step 6)
Draft practical completion certificate With the snag-clearance tracker Completion (step 7)
Checked as-built file As-built drawings, operating manuals, technical data sheets, test reports Completion (step 7)

At PRIMOE, decisions and commitments are recorded in writing, in project management software developed in-house and provided on every project. The deliverables to ask for are set out in detail in our guide MOEX: tasks and deliverables on a private contract.

A site about to start, or already under way?

Let’s talk about your site +33 1 72 68 22 71
Visualisation of the Roissy-en-Brie housing project: a building with continuous balconies and gabled roofs, seen from the street
Roissy-en-Brie (77) · project visualisation

Two housing projects under our construction supervision.

Roissy-en-Brie (77)

Brief
Housing
Service
Construction supervision
Status
Completed

A housing project under our construction supervision, from the first trade package to practical completion. Coordinating the contractors and keeping schedule and costs under control through to handover.

Pantin (93)

Brief
Housing
Service
Construction supervision
Status
In progress

A housing project in the inner suburbs of Paris, under our construction supervision. A constrained site where coordinating the contractors makes the difference on timescales.

See all our projects

When should you bring in MOEX?

As early as possible. Appointed before tendering, MOEX analyses the bids and reviews the contracts it will later have to enforce. It can also come in mid-construction, provided it starts with a written review of where things stand.

Three situations come up often.

  • The architect designed the project without a construction-phase role.

    MOEX takes over the construction phase, and the handover of drawings, their revisions and the contracts has to be organised.

  • The client is weighing up several contract set-ups.

    The choice between a general contractor and separate trade packages changes the number of interfaces to manage and the case for adding an OPC appointment (scheduling and coordination).

  • The site is going off track or has stalled.

    A site audit establishes the facts before any decision; then the recovery of the site can be organised.

If you need support before the works, for the brief, tendering or choosing the project team, the better fit is owner’s representation (AMO).

Frequently asked questions

Another question? Call us on +33 1 72 68 22 71 or email contact@primoe.fr.

Let’s talk about your site

What is the difference between MOEX and the design team?

The design team (architect, engineering consultants) designs the project and produces the drawings. MOEX takes over for the construction phase: it directs the works, checks compliance and takes the site through to practical completion. The two roles can be separated, and that is often good practice.

What do VISA, DET and AOR mean?

These are the three elements of the construction-phase appointment in French practice. VISA is the review of the construction drawings produced by the contractors, to check that they comply with the design. DET (direction de l’exécution des contrats de travaux), direction of the works contracts, covers site monitoring, meetings, site minutes and checking interim valuations. AOR (assistance aux opérations de réception), assistance at handover, runs through to clearing the snags. A MOEX appointment combines all three.

MOEX or main contractor: who directs the subcontractors?

The main contractor directs its subcontractors and answers to the client for their work. MOEX does not take its place: it checks that what is built complies with the drawings and the contracts, however the contractors are organised. With separate trade packages and no main contractor, coordination between contractors falls under the OPC appointment.

When should MOEX be appointed?

As early as possible, ideally before tendering: MOEX can then analyse the bids, check the quotes and secure the contracts. It can also be appointed mid-construction, in particular to take over a project that is going off track.

Do you take on sites already under way?

Yes. Recovering stalled or off-track sites is one of our specialities: audit of the current position, recovery plan, contract adjustments where needed, then management through to handover.

Where do you work?

In Paris and Île-de-France, where our team is based. For a project elsewhere, talk to us: we decide case by case, depending on the nature of the project.

How much does a MOEX appointment cost?

At PRIMOE, a construction supervision appointment on its own, without design, costs between 3 and 5% of the cost of the works excl. VAT. Where it falls in that range depends on the size of the project, the number of trade packages, the length of the works and, for refurbishment, the condition of the existing building. In France there is no fee scale: consultants’ fees are freely agreed, set in the contract as a fixed fee, per stage or as a percentage of the cost of the works. To compare proposals, look at the planned presence on site, the deliverables, the duration allowed for and what happens if the works overrun.

What is MOEX liable for, and must it be insured?

Under French law, a lead consultant bound to the client by a contract for works (louage d’ouvrage) is deemed a builder (Article 1792-1 of the Civil Code). Anyone who may incur ten-year latent defects liability (décennale) must be insured for it and provide proof when work starts on site (Article L241-1 of the Insurance Code). Ask for the insurance certificate and check that it covers the work entrusted.

Does MOEX declare practical completion?

No. Practical completion (réception) is the act by which the client declares that it accepts the works, with or without snags (Article 1792-6 of the Civil Code). MOEX organises the pre-completion inspections, proposes the snag list and assists the client; the decision and the signature are the client’s.

Contact

Let’s talk about your project.

A building to study, a construction site to run or restart, an operator to find: tell us where you stand.

3 rue Alfred Roll, 75017 Paris, France · Projects across Paris and Île-de-France

Or describe your project in a few lines.

Your details are used only to reply to you. They are never passed on or used for marketing. Your data (in French)