The works are nearly finished, the contractors are asking for practical completion, and the operator or the buyers are waiting for the keys. For the client, this is the signature that commits it most: the date of the certificate starts the warranties, and anything not recorded in it as a snag becomes hard to claim.
This guide describes practical completion under a French private works contract, based on the texts and decisions as read on Légifrance on 17 November 2026. It replaces neither your contract nor a lawyer in the event of a dispute.
What is practical completion, and who declares it?
Practical completion is the client’s decision. French law defines it as “the act by which the owner declares that it accepts the works with or without reservations”. It takes place “at the request of the more diligent party, either amicably or, failing that, by the court”, and is “in any event, declared in the presence of the parties” (Article 1792-6 of the Civil Code).
- The client signs. The lead consultant organises, records and recommends; it does not accept the works on the client’s behalf.
- The contractor can request it, as can the client: whoever does so is the “more diligent party”.
- Both sides are heard. The contractors concerned are invited and put forward their observations.
The contract’s special administrative conditions (CCAP) often set out the procedure: notice to attend, form of the certificate, completion package by package or for the whole works. If they refer to the NF P 03-001 standard, its clauses apply: reread them before sending out the notices.
Completion with or without snags: what is the difference?
Accepting with snags means accepting the works while listing what still has to be put right or finished. Accepting without snags means declaring that nothing visible remains to be corrected. The snags are the very subject of the one-year defects warranty (garantie de parfait achèvement).
This warranty, owed by the contractor for one year from practical completion, “extends to the repair of all defects reported by the owner, either by means of reservations recorded in the practical completion certificate or by written notice for those that come to light after practical completion” (Article 1792-6). It does not cover the effects of normal wear and tear or use.
Visible defects not recorded as snags
A defect that is visible on the day of practical completion but not mentioned in the certificate is, in principle, lost: “acceptance without reservations covers apparent defects”. The same decision states that building damage insurance (dommages-ouvrage) applies to defects of a ten-year (décennale) nature “that appeared after it” (Cour de cassation, 3rd civil chamber, 11 May 2022, No. 21-15.608).
The rule fits in one sentence: if you can see it, record it as a snag, even if it looks minor.
What is the pre-completion inspection (OPR)?
The pre-completion inspection (opérations préalables à la réception, OPR) consists of the visits, package by package, that produce the snag list before the client signs. The Civil Code does not describe it: it is governed by the works contract and the lead consultant’s appointment.
For French public clients, the lead consultant’s appointment may include “assistance to the client during the practical completion procedures and during the one-year defects warranty period” (Article R2431-1 of the Public Procurement Code). On a private contract, this vocabulary serves as a reference; the lead consultant’s contract sets out what is entrusted to it.
What is checked during the inspection
- completion of the works provided for in the contract, room by room;
- visible defects: appearance, finishes, fixings, joints;
- the operation of the equipment;
- the tests and inspections required by the contract, and the reports that evidence them;
- the documents the contractors must hand over, including the as-built file (DOE).
Each snag is written so that it can be cleared without argument: the trade package, the location, the nature of the defect, what is expected.
What does the practical completion certificate contain?
The practical completion certificate (procès-verbal de réception) records the client’s decision and its date. The Civil Code sets no template, but gives it a precise role: it is where the snags that bring the one-year defects warranty into play are “recorded” (Article 1792-6). In practice, it contains:
- the identification of the project, the client and each contractor concerned, package by package;
- the date of practical completion, which starts the warranties;
- the decision: completion without snags, completion with snags, or a reasoned refusal;
- the snag list, in an appendix if it is long, with the trade package responsible for each snag;
- the deadlines for clearing the snags, if they have been agreed with the contractors;
- the signatures of the client and the contractors, or a note that a contractor was invited but absent.
The contract may require other entries: refer to its CCAP.
How are the snags cleared, and within what period?
French law sets no single deadline for clearing snags. It leaves it to agreement: “the time needed to carry out the repair work is set by mutual agreement between the owner and the contractor concerned” (Article 1792-6). The outer limit is that of the one-year defects warranty: one year from practical completion.
The same article sets out what follows:
- Without agreement, or if the deadline is missed, the work may, “after formal notice has gone unheeded, be carried out at the expense and risk of the defaulting contractor”.
- Clearance must be formally recorded. Completion of the work required under the warranty is established “by mutual agreement or, failing that, by the court”. A snag is cleared when the remedial work has been checked and that finding put in writing, not when the contractor says so.
- Building damage insurance (dommages-ouvrage) may apply, if it was taken out. In principle it takes effect after the one-year defects warranty, but it also covers the necessary repairs where, “after practical completion, and after formal notice has gone unheeded, the contractor has not performed its obligations” (Article L242-1 of the Insurance Code). It covers damage of a ten-year (décennale) nature.
Tracking is done snag by snag: trade package, agreed deadline, date of the remedial work, date clearance was recorded. See our guide on payment certificates.
In short: the deadline for clearing the snags is agreed with each contractor, within the one-year defects warranty period. Without agreement, or in the event of delay, a formal notice opens the right to have the work done at the contractor’s expense. The clearance of each snag is recorded in writing.
What does practical completion trigger, and from when?
Under French law, the date of practical completion is the starting point of the builders’ statutory warranties.
Scroll the table sideways →
| Warranty | What it covers | Duration, from practical completion | Legal text |
|---|---|---|---|
| One-year defects warranty (parfait achèvement) | Defects recorded as snags in the certificate and those notified in writing after practical completion | One year | Civil Code, Article 1792-6 |
| Equipment warranty (bon fonctionnement) | The “other items of equipment” of the building referred to in Article 1792-3 | At least two years | Civil Code, Articles 1792-3 and 1792-4-1 |
| Ten-year latent defects liability (décennale) | Damage that compromises the structural soundness of the building or makes it unfit for its intended purpose | Ten years | Civil Code, Articles 1792 and 1792-4-1 |
| Building damage insurance (dommages-ouvrage) | Payment for the repair of damage of a ten-year nature | Takes effect after the one-year defects warranty; applies earlier in the cases set out in the text | Insurance Code, Article L242-1 |
| Retention or guarantee | Performance of the work needed to clear the snags | Released after one year, unless a reasoned objection is raised | Law No. 71-584 of 16 July 1971, Articles 1 and 2 |
The texts: the items of equipment concerned “are covered by a warranty of proper functioning for a minimum of two years from its acceptance” (Article 1792-3 of the Civil Code). Every builder is strictly liable for damage that “compromises the structural soundness of the building” or makes it “unfit for its intended purpose”, unless an external cause is proven (Article 1792 of the Civil Code). Builders are released from this liability “ten years after practical completion of the works” (Article 1792-4-1 of the Civil Code).
An uncertain completion date makes every one of these deadlines uncertain.
How does retention work?
On a French private works contract, interim payments “may be reduced by a retention of no more than 5 per cent of their amount”, which contractually secures performance of the works “to satisfy, where applicable, the reservations made at acceptance” (Article 1 of Law No. 71-584 of 16 July 1971). Retention exists only if the contract provides for it.
- The client deposits a sum equal to the retention with a stakeholder accepted by both parties or appointed by the president of the court.
- No retention is made if the contractor provides, for the same amount, a personal, joint and several guarantee from a financial institution on a list set by decree.
- One year after practical completion, with or without snags, the guarantee is released or the deposited sums are paid to the contractor, “even in the absence of a formal release”, unless the client has notified the stakeholder or the guarantor, by registered letter, of “its objection on the grounds that the contractor has failed to perform its obligations”. An abusive objection exposes the client to damages (Article 2 of Law No. 71-584 of 16 July 1971).
What if practical completion is refused, disputed or never signed?
Since practical completion is the act by which the client declares that it accepts the works, the client is not obliged to declare it if it considers that the works cannot be accepted, subject to review by the court, to which the contractor may apply. Article 1792-6 sets no form for a refusal: give your reasons in writing.
Completion declared by the court
When the parties cannot agree, practical completion takes place “failing that, by the court” (Article 1792-6). Either party may apply to the court; the case is prepared with a lawyer, on the basis of the site minutes, the formal findings and the snag lists.
Tacit completion
Even without a certificate, a court may find that practical completion took place. The Cour de cassation (France’s highest court in civil matters) holds that, under Article 1792-6, “taking possession of the works and paying for them give rise to a presumption that the owner unequivocally intended to accept them with or without reservations” (Cour de cassation, 3rd civil chamber, 18 April 2019, No. 18-13.734). Occupying the premises and paying may therefore lead to a presumed completion whose date and snags are written down nowhere. Before moving in or paying the final balance, sign the certificate.
Related cases: a contractor that leaves before the end (site abandonment: what to do) and late completion (construction delays: proof and penalties).
Practical completion: the questions clients ask
What is the deadline for clearing the snags?
French law sets no single deadline: the time allowed for remedial work is agreed between the client and each contractor. It falls within the one-year defects warranty, which runs from practical completion. Without agreement, or in the event of delay, a formal notice that has had no effect allows the work to be carried out at the contractor’s expense.
What happens if a visible defect was not recorded as a snag?
In principle, it is waived by practical completion: the Cour de cassation holds that acceptance without reservations covers apparent defects. Building damage insurance (dommages-ouvrage) may apply to a defect of a ten-year (décennale) nature that appears after practical completion.
Can you move in before practical completion?
It is risky. The Cour de cassation holds that taking possession of the works and paying for them give rise to a presumption that the client intended to accept them. Sign off practical completion before occupying the premises.
Can practical completion be declared package by package?
The Civil Code neither requires nor prohibits it: the contract decides. With separate trade packages, one certificate per contractor lets each of them know its own snags. Check your CCAP.
When is the retention returned?
One year after practical completion, with or without snags, the guarantee is released or the deposited sums are paid to the contractor, unless a reasoned objection has been notified by registered letter (Article 2 of Law No. 71-584 of 16 July 1971).
Can the contractor obtain practical completion if the client refuses it?
It can request it, since practical completion takes place at the request of the more diligent party. Failing agreement, it can apply to the court, which then declares completion itself. So give the reasons for any refusal in writing.
How PRIMOE prepares for practical completion as construction supervisor
Practical completion is the client’s decision: we prepare it. In a construction supervision (MOEX) appointment, assistance with practical completion continues until the snags are cleared. In practice:
- Before practical completion, we organise the pre-completion inspection: inspection of the works package by package with the contractors, snag list, checks on the required tests and inspections. You receive the inspection reports and the snag lists by package.
- At practical completion, we assist you and hand you the draft practical completion certificate, with the snag tracker.
- Afterwards, we follow each snag until its clearance has been recorded, then collect and check the as-built file (DOE) before handing it over to you.
With separate trade packages, coordinating the contractors falls under the scheduling and coordination (OPC) service. See also our guide Construction supervision (MOEX): tasks and deliverables and our fees for MOEX, OPC and owner’s representation (AMO). To prepare practical completion of a project in Paris and Île-de-France: contact@primoe.fr.
Example: in Roissy-en-Brie, PRIMOE ran practical completion and the clearing of snags for 46 homes, handed over in July 2026 after 16 months of works.