Project rendering
Pantin (93) · 2026 – 2027
15 homes and a shop in Pantin, Avenue Jean Lolive
An apartment building in the inner suburbs of Paris (Île-de-France), built over the Metro line 5 tunnel. PRIMOE has provided construction supervision (MOEX) and scheduling and coordination (OPC) since February 2026, and restarted the works after the main contractor defaulted. Completion is scheduled for July 2027.
Key facts
- Location
- Pantin (93), Avenue Jean Lolive
- Client
- SCI BCD
- Brief
- 15 flats, from one-room (T1) to five-room (T5), and a ground-floor shop
- Floor area
- 1,338 m² of floor area (surface de plancher) on a 409.60 m² plot
- Label
- BiodiverCity, application under way
The project
- Height
- Ground plus five storeys over a basement, zinc roof
- Façade
- White stained architectural concrete, loggias
- Foundations
- 20 bored piles socketed into the limestone
- Constraint
- Metro line 5 tunnel beneath the site: anti-vibration bearings with a natural frequency of no more than 8 Hz
The building
- Construction supervision (MOEX) and OPC
- PRIMOE, since February 2026
- Main contractor
- ERI CONSTRUCTION
- Technical inspector
- ALPES CONTRÔLES
- Scheduled handover
- July 2027
The project team
Our role on the project
PRIMOE has provided construction supervision (MOEX) and OPC since February 2026. When the main contractor stopped meeting its obligations in summer 2026, we put its default on record in writing, handled the termination of its contract, then restarted the works with a new contractor, with rebuilt tender documents and a construction schedule that is being met.
Today we direct the works and manage the schedule through to practical completion: approval of construction drawings, site meetings and site minutes, checking interim valuations, and preparing the pre-completion inspections.
Milestones
PRIMOE appointed: construction supervision (MOEX) and OPC
Structural works halted above the ground floor
Contract with the defaulting main contractor terminated
New contract signed, works resumed
Scheduled completion
The site in pictures