Developing a retail brand means turning an opening plan into stores that actually open, on the planned date and at the planned cost. For a development team, the question is never just finding premises: it is applying the same method to every site, so that locations can be compared and decisions made quickly. This guide describes the six steps, what is decided at each one, the mistakes that cost months and, for France, the authorisations to build into the timetable.
Why give a retail brand’s property development a structure?
Because a network opens in very different settings (town centre, edge of town, shopping centre) and each opening commits the brand for the term of a lease. A common method makes it possible to compare sites, spot early on those that will not hold up, and avoid redoing the same checks every time.
Two benchmarks show what is at stake. According to France’s statistics office, Insee (2025), retail businesses are the least likely to last: 64% of those created in the first half of 2018, excluding micro-entrepreneurs, were still active five years later, against 69% across all sectors. And the market remains active: according to BNP Paribas Real Estate (fourth-quarter 2025 review, in French), retail investment in France again reached €3 billion in 2025, up 14% on 2024.
Scroll the table sideways →
| Step | The question to settle | The output | The decision |
|---|---|---|---|
| 1. Search | Which premises match the specification? | A shortlist of sites | Visit or rule out |
| 2. Assessment | Does the site suit the concept and the customer base? | A site sheet: catchment area, footfall, technical points, competition | Study or rule out |
| 3. Feasibility | Can we open there, at what cost, with which authorisations? | A technical, regulatory and financial feasibility file | Commit or not |
| 4. Structuring | On what terms do we commit? | The lease or BEFA signed, the authorisation applications filed | Sign, subject to conditions precedent |
| 5. Works | Are the works on time, on budget and true to the concept? | A monitored site, site minutes, practical completion | Accept the works, with or without snags |
| 6. Opening | Is everything in order to receive the public? | Authorisations obtained, snags cleared | Open |
In short: six steps, six written decisions. Search and assessment rule out poor sites at little cost; feasibility avoids signing a lease on premises that cannot be traded from; structuring, works and opening keep to the timetable announced to the network.
Step 1: how do you find the right premises?
By starting from a written specification, not from listings. It sets the target towns and neighbourhoods, the type of location, the floor area, the shopfront length, the concept’s technical constraints and the rent the business can bear. The search then covers premises on the market as well as those not yet advertised.
What is at stake
The search turns the expansion strategy into criteria that can be checked: geographical areas, type of site (high street, ground floor of a building, retail park, shopping centre), floor area range, leasing or buying. Without this framework, every viewing is judged on impressions.
Common mistakes
- Starting the search without a specification: pointless viewings pile up.
- Sticking to public listings, when many premises become vacant without ever being advertised.
- Targeting a wider territory than the network can open and supply.
Where PRIMOE comes in
We study assets in the Paris region for their owners, and present those that are ready to operators whose business fits: this is the PRIMOE Activation path. To understand what the owner across the table is preparing, read how to find an operator for a retail unit.
Step 2: how do you assess a site?
By testing it against the specification on four points: the catchment area, access and footfall, the technical features of the premises, and competition and vacancy nearby. A site is assessed before any discussion of rent: a good price makes up neither for missing customers nor for insufficient ceiling height.
What is at stake
The catchment area is the area the store’s customers come from. It is divided into primary, secondary and tertiary zones, from regular to occasional customers, and is measured in actual travel time rather than distance. The acceptable time depends on the type of shop: a convenience store is reached on foot, a destination store by car or public transport.
Access and footfall: pedestrian and vehicle flows, parking, public transport, visibility of the shopfront from the main roads. A detail of the layout can cancel out the effect of a good address, for example an avenue that is hard to cross between the premises and the shop that draws people to the area.
Technical features: clear height under beams, structure, utilities, electrical capacity, extraction, delivery access. They must accommodate the concept without disproportionate works.
Competition and vacancy: direct competitors in the primary zone, how long neighbouring shops have been there and how often they change, empty units in the street. As a benchmark, the national retail vacancy rate in France reached 11.6% in 2025 according to Codata (LSA, 2026).
Common mistakes
- Choosing on rent alone, without studying the catchment area.
- Discovering a technical constraint, such as height or deliveries, after weeks of discussion.
- Ignoring vacancy in the street, which signals an area losing footfall.
- Not cross-checking footfall against local shopping habits and where competitors actually are.
Where PRIMOE comes in
On the technical side. We record what the premises actually allow: usable dimensions, structure, utilities, access, condition of the building shell and roof. The commercial analysis remains the brand’s, with its own geomarketing tools.
Step 3: is the site technically, legally and financially feasible?
Feasibility answers three questions before any commitment. Can the building take the concept, and what works will that require? Which authorisations are needed, and how long will they take? Is the full cost of setting up affordable given the expected turnover? A negative answer at this stage costs only the study.
What is at stake
Technical: whether the structure, utilities and shopfront are compatible with the concept, the works required and how long they will take. This is what our feasibility study covers.
Regulatory: the use permitted by the local zoning plan (PLU), the planning authorisation required, the rules for establishments open to the public (ERP, établissements recevant du public) and, depending on the sales area, a retail operating authorisation (AEC) reviewed by the departmental retail planning committee (CDAC). Under French law, the thresholds are set by Article L752-1 of the Commercial Code:
Scroll the table sideways →
| Type of project | Threshold that triggers an AEC |
|---|---|
| Creation of a retail store | Sales area over 1,000 m² |
| Extension of a retail store | Store that has reached 1,000 m², or will exceed it |
| Change of trading sector | Area over 2,000 m², or over 1,000 m² if the new activity is predominantly food |
| Creation of a retail complex | Total sales area over 1,000 m² |
| Reopening on the same site after three years without trading | Sales area over 2,500 m² |
| Creation or extension of a collection point for goods ordered remotely, designed for access by car (a “drive”) | Any creation or extension |
When the project needs a building permit, that permit serves as the AEC once the committee has given a favourable opinion (Article L425-4 of the Town Planning Code). The procedure, its time limits and appeals are set out in our guide Retail planning consent (CDAC) in France.
Financial: any key money, rent, service charges, taxes, fit-out works and fees, set against the turnover expected on the site.
Common mistakes
- Discovering the need for CDAC authorisation after signing a preliminary agreement.
- Underestimating the works for lack of a survey of the existing building.
- Approving a site on the advertised rent, without counting service charges, taxes and fit-out.
Where PRIMOE comes in
This is the core of our work: reading the building, the rules that apply to it and the cost of the works, then setting it all down in a file that supports a decision. In Saint-Ouen (93) and Boulogne-Billancourt (92), we are carrying out, for two residential projects, the feasibility study for the planning change of use, the sketch design and the preliminary design; the method is the same for a retail unit.
In short: feasibility comes before signing, not after. It tells you whether the premises can take the concept, which authorisations are needed and what the full set-up will cost. Above 1,000 m² of sales area, it includes the CDAC procedure.
Step 4: how do you set up the deal (BEFA, lease, authorisations)?
Structuring sets the terms of the commitment and starts the authorisations. The brand and its advisers settle the contract, whether a commercial lease, an off-plan lease (BEFA, bail en l’état futur d’achèvement) or a purchase, with the conditions precedent that protect the brand. In parallel, the authorisation applications are filed so that the review periods start running straight away.
The French commercial lease: what should you check?
- The term: at least nine years, with the tenant entitled to give notice at the end of each three-year period, six months in advance (Article L145-4 of the Commercial Code).
- Service charges and works: the lease contains a precise and exhaustive inventory of service charges, taxes and levies, with how they are shared (Article L145-40-2 of the Commercial Code).
- Rent changes: where the lease contains an indexation (sliding scale) clause, a review can be requested as soon as the rent has changed by more than a quarter (Article L145-39 of the Commercial Code).
- Rent payment: since Law No. 2026-403 of 26 May 2026, the tenant of premises used for retail or wholesale trade, or for services, can ask to pay its rent monthly, provided it has no arrears (Article L145-32-1 of the Commercial Code).
- Guarantees: for the same premises, the sums and guarantees required from the tenant cannot exceed one quarter’s rent, in leases signed or renewed since that law (Article L145-40 of the Commercial Code).
To test a location before committing for nine years, there is a shorter contract: see our guide to the short-term commercial lease (bail dérogatoire).
The BEFA: when the premises do not exist yet
The off-plan lease is signed before the premises are built or completed. It has two phases: the construction period, governed by general French contract law, then the commercial lease itself, from delivery. The earlier it is signed, the more the conditions precedent matter: building permit obtained and final, third-party appeal periods expired, CDAC authorisation where applicable, start and completion dates for the works. The contract also sets out what happens in the event of delay: penalties, then a right for the tenant to withdraw.
Which authorisations should be filed, and on what basis?
Scroll the table sideways →
| Authorisation | When it is needed | Text |
|---|---|---|
| Building permit or prior declaration | New construction, shopfront alteration, planning change of use, depending on the works | Town Planning Code |
| Retail operating authorisation | Above the sales area thresholds; the permit serves as the authorisation after a favourable CDAC opinion | Article L752-1 of the Commercial Code and Article L425-4 of the Town Planning Code |
| Works authorisation for an ERP | Creation, fit-out or alteration of an building open to the public: the authority checks accessibility and, depending on the occupancy and type of establishment, fire safety. The building permit serves as this authorisation once that authority has approved it | Article L122-3 of the Construction and Housing Code |
| Shop sign consent | On protected buildings and in protected places, and within the area covered by local advertising regulations | Article L581-18 of the Environmental Code |
A recent change for ERPs: in the version in force since 28 May 2026, Article L122-3 provides that a declaration of compliance certified by a third party may replace the works authorisation for certain establishments of less than 300 m² that keep the same activity. The conditions are left to a decree: check with your lead consultant whether your premises qualify.
Common mistakes
- Signing a BEFA with no conditions precedent and no delay clause.
- Confusing practical completion of the works, delivery by the developer and making the premises available under the lease: three separate acts, often on the same day.
- Leaving the review periods for the works authorisation and the shop sign consent out of the opening timetable.
- Not reading the rent indexation clause.
Where PRIMOE comes in
On the authorisations and on the technical documents of the contract: specification of landlord’s and tenant’s works, scope boundaries, timetable. This is our project structuring service. Rent and clauses are negotiated between the brand and the landlord, with their lawyers.
In short: structuring runs on two fronts at once. The contract, with its conditions precedent and its split of works; the authorisations, filed early so that their time frames do not push back the opening. Since May 2026, French law also caps guarantees and governs how often rent is paid.
Step 5: how do you manage the works?
With a named person in charge, a detailed schedule and written site minutes after every site meeting. Construction supervision (MOEX, maîtrise d’œuvre d’exécution) directs the works and checks that they comply; scheduling and coordination (OPC, ordonnancement, pilotage et coordination) organises when each contractor works. On a store, both services are often entrusted to the same firm.
What is at stake
Fitting out a store is short and intense: the trades follow one another within a few weeks, in premises that the landlord sometimes hands over late. Site management follows the works schedule, coordinates the brand’s contractors and the landlord’s, checks that the work matches the concept specification and deals with the unexpected.
Practical completion (handover) closes this step: under French law, it is the act by which the client accepts the works, with or without snags. It starts the one-year defects warranty, owed by the contractor for defects listed as snags at handover or reported in writing afterwards (Article 1792-6 of the Civil Code).
Common mistakes
- No one in charge: the brand coordinates the landlord, the contractors and its own suppliers on its own.
- A delay known on site, but not to those who announced the opening date.
- A departure from the concept (layout, materials, lighting) discovered on the day of handover.
- No procedure for reporting defects during the one-year warranty period.
Where PRIMOE comes in
As construction supervisor and OPC consultant, in Paris and Île-de-France. We are currently the MOEX on a residential project in Pantin (93) and have completed one in Roissy-en-Brie (77). Two rules apply to all our sites: no more than three sites per project manager, and written site minutes after every meeting. The split of roles is explained in our guide MOEX, OPC, AMO: who does what.
Step 6: what should be checked before opening?
Three things: the authorisations have been obtained; practical completion has been certified and the snags that hinder trading have been cleared; the shop sign has been installed in line with the rules; the teams, stock and till systems are ready. Only then is the opening date announced.
What is at stake
The end of the works and the start of trading overlap: delivery of furniture, stocking the shelves, staff training, testing of installations. A single timetable for works and operations stops one waiting for the other.
Above the sales area thresholds, there is one more formality: one month before opening to the public, the AEC holder sends the prefect a certificate of compliance drawn up by an approved body, failing which trading is deemed unlawful (Article L752-23 of the Commercial Code).
How long from the first viewing to opening?
There is no standard duration, and we do not publish one. The time frame depends on three factors that the feasibility study can quantify site by site: the type of premises, existing or to be built; the authorisations needed and their review and appeal periods; the extent of the works. Premises to be built under a building permit do not follow the timetable of a shop taken over as it stands.
Common mistakes
- Announcing an opening date before the authorisations and practical completion are in hand.
- Not coordinating the end of the works with stock, recruitment and training.
- Discovering at the end of the process that a shop sign consent or an AEC is missing.
In short: you open when the authorisations are obtained, practical completion is certified and the teams are ready. The date is set from the site’s actual timetable, drawn up at the feasibility stage, not from an average.
What support is there for a retail brand’s property development?
Three professions share the process. Finding premises and negotiating the lease are the job of the brand and its advisers. Feasibility, authorisations and running the works are the job of a lead consultant or an owner’s representative. PRIMOE does the latter, in Île-de-France.
In practice, a brand can entrust a site to us: the study of what the premises allow, the authorisations file, then the works through to practical completion and clearing the snags. This is the PRIMOE Development path for the upstream work, then PRIMOE Delivery for the works.
A site in the Paris region to study before you commit? Email us at contact@primoe.fr with the address, the floor area and your concept.
Time frames, BEFA, CDAC: questions from development teams
What is property development for a retail brand?
It covers everything a retail network does to open new stores: finding premises, commercial and technical assessment of sites, feasibility study, setting up the lease and authorisations, fit-out works, opening. In structured networks, it is run by a development department, which presents each site to a site approval committee.
How long does it take to open a new store?
It depends on the site. A shop taken over as it stands, with no special authorisation, opens much faster than premises to be built under a building permit, or a store of more than 1,000 m² that has to go before the CDAC. The reliable timetable is the one the feasibility study sets for the site, authorisation by authorisation.
What criteria should a retail brand use to choose premises?
The catchment area and its customers, pedestrian and vehicle footfall, visibility, parking and public transport, competition and vacancy nearby, then the technical criteria: usable floor area, clear height, shopfront, deliveries, electrical capacity, extraction. Add to these the permitted use and the full cost of setting up: rent, service charges and works.
What is a BEFA?
An off-plan lease (bail en l’état futur d’achèvement): a French commercial lease signed before the premises are built or completed. It lets the brand secure a unit in a new development. Its security lies in its conditions precedent (final permit, authorisations obtained), its delivery dates and what it provides for in the event of delay.
When does opening a store require CDAC authorisation?
When the project creates a store or a retail complex of more than 1,000 m² of sales area, or extends a store beyond that threshold. A change of trading sector requires it above 2,000 m², or 1,000 m² for food. Below that, opening is governed only by planning authorisations and the rules for establishments open to the public.
Is authorisation needed to fit out an existing shop?
Yes, in principle. Under French law, a shop is an building open to the public: works that create, fit out or alter it must be authorised before they are carried out, with the authority checking accessibility and, where applicable, fire safety. A shopfront alteration or a new shop sign may require a separate authorisation.
What does the law of 26 May 2026 change for a retail brand’s lease?
Two points, as read in the current Commercial Code. The tenant of retail or service premises can ask to pay rent monthly, provided it has no arrears. And, in leases signed or renewed since that law, the sums and guarantees required from the tenant cannot exceed one quarter’s rent.