You are creating, enlarging or converting retail space and wondering whether the project has to go before the CDAC. Under French law, the rule fits in one line: above certain sales area thresholds set by the Commercial Code, nothing can open without a retail operating authorisation. This guide covers the thresholds, the committee’s membership, the content of the application, review periods, appeals and penalties, article by article, using the texts in force on the date of the last update.
What is the CDAC, and when is authorisation required?
The CDAC is the committee, chaired by the prefect (the State’s representative in the department), that authorises retail projects above a sales area threshold. Its authorisation, the AEC, is required to create or extend a retail store or a retail complex of more than 1,000 m², and for a few other operations listed by law.
The committee was created by the Economic Modernisation Act of 4 August 2008 (loi de modernisation de l’économie). It reviews new stores, extensions, changes of trading sector and some store reopenings.
Which sales area thresholds trigger an AEC?
The thresholds are set by Article L752-1 of the Commercial Code. France’s Directorate-General for Enterprise publishes an official overview (in French), updated on 14 January 2026.
Scroll the table sideways →
| Operation | Sales area threshold |
|---|---|
| Creation of a retail store, by new construction or conversion of an existing building | More than 1,000 m² |
| Extension of a retail store | Store that has already reached 1,000 m², or will exceed it as a result of the project |
| Change of a store’s trading sector | More than 2,000 m², or more than 1,000 m² if the new activity is predominantly food |
| Creation of a retail complex | More than 1,000 m² in total |
| Extension of a retail complex | Complex that has already reached 1,000 m², or will exceed it as a result of the project |
| Reopening to the public, on the same site, of a store whose premises have not traded for three years | More than 2,500 m² |
| Creation or extension of a permanent collection point for goods ordered remotely, designed for access by car (a “drive”) | No threshold: any creation or extension |
A “drive” built into a store that was already open to the public when the law of 24 March 2014 was published is exempt from authorisation if it creates no more than 20 m² of floor area (same article).
Which projects are exempt?
Article L752-2 of the Commercial Code, in the version in force since 28 May 2026, exempts in particular:
- the merging of the sales areas of neighbouring stores, without creating any additional area, up to 2,500 m², or 1,000 m² where the new activity is predominantly food;
- pharmacies, and car and motorcycle dealerships;
- covered halls and retail food markets on public land whose creation is decided by the municipal council;
- stores inside airports that are open only to ticketed passengers;
- the parts of public land allocated to railway and coach stations in town centres, up to 2,500 m²;
- property developments that combine a shop and housing in a town centre, within an area covered by a territorial revitalisation operation (ORT, opération de revitalisation de territoire), where the sales area is less than a quarter of the residential floor area.
Within an ORT that includes a town centre, projects that involve no land take (artificialisation des sols) are exempt from the AEC. The ORT agreement may, however, reinstate the requirement above a threshold it sets, which cannot be lower than 5,000 m², or 2,500 m² for predominantly food stores (Article L752-1-1 of the Commercial Code).
Can a project under 1,000 m² go before the CDAC?
Yes. In municipalities with fewer than 20,000 inhabitants, the mayor, or the president of the inter-municipal authority (EPCI) responsible for planning, on receiving a building permit application for a retail facility of 300 to 1,000 m², may propose to their council that the project be referred to the CDAC. The option exists in every municipality when the project involves land take. The committee then rules within one month, and an unfavourable opinion prevents the permit from being granted (Article L752-4 of the Commercial Code).
In short: above 1,000 m² of sales area, creating or extending a store or a retail complex requires an AEC. The threshold rises to 2,000 m² for a change of trading sector and to 2,500 m² for a reopening after three years. A “drive” needs one whatever its size.
Building permit or AEC alone: which procedure for your project?
It depends on the works. If the project needs a building permit, you file a single application at the town hall: the permit serves as the AEC once the CDAC has given a favourable opinion. If no permit is required, the application goes directly to the committee’s secretariat, and the committee grants the authorisation.
The permit that serves as the AEC is provided for by Article L425-4 of the Town Planning Code. Two practical consequences follow. An unfavourable opinion from the committee blocks the permit. And a substantial change to the retail project, even one with no effect on planning rules, requires a new AEC application.
That is why the question arises at the feasibility study stage, before any design work: the sales area, the type of activity and the location decide the procedure, and therefore the timetable. In our project structuring service, the AEC is one of the authorisations we identify before the permit application is filed.
In short: with a building permit, a single application filed at the town hall, and a permit that serves as the AEC after a favourable CDAC opinion. Without a permit, an AEC application sent to the committee’s secretariat. Either way, the project cannot open without this authorisation.
Who sits on the CDAC?
Outside Paris, the CDAC has eleven members and is chaired by the prefect: seven elected officials and four qualified persons. In Paris it has eight: five elected officials and three qualified persons. The prefect chairs the meeting but does not vote.
Membership is set by Article L751-2 of the Commercial Code, in the version in force since 28 May 2026 (Law No. 2026-403 of 26 May 2026).
- The seven elected officials: the mayor of the municipality where the project is located, the president of the tax-raising EPCI of which the municipality is a member, the president of the body responsible for the territorial coherence scheme (SCoT, the strategic plan for the wider area), the president of the departmental council, the president of the regional council, one representative of the mayors and one representative of the inter-municipal authorities of the department, or their representatives.
- The four qualified persons: two with expertise in consumer affairs and consumer protection, two in sustainable development and land-use planning.
- In Paris: the Mayor of Paris, the mayor of the arrondissement where the project is located, an arrondissement councillor appointed by the Council of Paris, a deputy mayor of Paris and a regional councillor, with three qualified persons.
The same article contains three points worth knowing before the meeting. For every new project, the committee hears the town-centre retail manager and the traders’ associations of the municipality and neighbouring municipalities. The chamber of commerce and industry, the chamber of trades and crafts and the chamber of agriculture do not sit on the committee, but may carry out studies at the prefect’s request. Lastly, if the catchment area extends beyond the department, the prefect adds at least one elected official and one qualified person from each other department concerned.
The committee can deliberate if a majority of its members are present. Failing that, a second meeting is held at least three days after the new notice of meeting is sent, with the quorum reduced to one third of the members (Article R752-15 of the Commercial Code).
What goes into an AEC application?
The application presents the applicant, the land, the project and its effects on land-use planning, sustainable development and consumer protection. An impact assessment carried out by an independent body approved by the prefect must be appended. Without it, the application is incomplete.
Who can apply?
The owner of the land or building, anyone holding a title that entitles them to carry out the works, or their authorised agent. Where the project does not need a building permit, the application may also come from the person entitled to operate the building commercially (Article R752-4 of the Commercial Code).
Which documents are needed?
- the applicant’s identity, and the location, address and area of the land;
- an extract from the land registry plan, a 1:25,000 map, an annotated aerial view, photographs and elevation drawings;
- a presentation of the project and its effects, criterion by criterion (Article R752-6 of the Commercial Code);
- the impact assessment.
For a project without a building permit, the application is sent to the CDAC secretariat in two copies, one of them in electronic form (Article R752-11 of the Commercial Code). With a permit, it goes with the permit application filed at the town hall; since 1 January 2022, municipalities with more than 3,500 inhabitants have received and processed these applications electronically (Article L423-3 of the Town Planning Code).
What must the impact assessment show?
It assesses the project’s effects on the vitality and economic development of the town centre of the host municipality, of the neighbouring municipalities and of the inter-municipal area, and on employment. It draws in particular on demographics, the retail vacancy rate and the retail floor space already present in the catchment area. The applicant must also show that no brownfield site in the town centre, and then on the outskirts, could accommodate the project (Article L752-6 of the Commercial Code).
And if the project involves land take?
The same article lays down a principle of prohibition: no AEC may be granted for a new store or an extension that involves land take. An exemption remains possible, subject to conditions, for projects of less than 10,000 m² of sales area; between 3,000 and 10,000 m², it requires the prefect’s binding opinion (avis conforme). A bare site on the edge of town is therefore no longer as feasible as an existing building to convert. On the latter, see our guide to converting an industrial building.
In short: the AEC application brings together the applicant’s identity, plans and views of the site, a presentation of the project’s effects and an impact assessment entrusted to an independent body approved by the prefect. A project that involves land take is refused in principle, unless it qualifies for a strictly limited exemption.
How does the review work, and how long does it take?
The CDAC rules within two months of the application being referred to it. If it has not ruled by then, its decision is deemed favourable. It votes by an absolute majority of the members present, and its decision is notified to the applicant within ten days of the meeting.
These rules are set out in Article L752-14 of the Commercial Code. The period runs from receipt of a complete application: if no further documents are requested within fifteen clear days, the application is deemed complete (Article R752-12 of the Commercial Code for a project without a permit, Article R752-10 of the Commercial Code for a project with a permit).
Scroll the table sideways →
| Stage | Time limit | Text |
|---|---|---|
| Check of the application by the CDAC secretariat | 15 clear days; if no documents are requested, the application is deemed complete | Articles R752-10 and R752-12 of the Commercial Code |
| Application sent to committee members | At least 10 days before the meeting; review reports, at least 5 days before | Article R752-13 of the Commercial Code |
| CDAC decision or opinion | 2 months from referral; after that, the decision is deemed favourable | Article L752-14 of the Commercial Code |
| Notification to the applicant and publication | 10 days after the meeting | Article R752-19 of the Commercial Code |
| Appeal to the national committee (CNAC) | 1 month | Article L752-17 of the Commercial Code |
| CNAC opinion or decision | 4 months; after that, the CDAC opinion is deemed confirmed | Article L752-17 of the Commercial Code |
Members receive the application at least ten days before the meeting (Article R752-13 of the Commercial Code). Within ten days of the meeting, the prefect notifies the decision or opinion to the applicant and, where a permit is needed, to the authority that grants it. If the opinion or decision is favourable, an extract is published in two regional or local newspapers, at the applicant’s expense (Article R752-19 of the Commercial Code).
In short: allow fifteen clear days for the application to be confirmed complete, two months for the CDAC decision, ten days for its notification, then a one-month appeal period. If there is an appeal, the national committee has four months. These are the periods to write into the project timetable.
How can a CDAC decision be challenged?
Any challenge must first go to the national retail planning committee (CNAC, Commission nationale d’aménagement commercial), within one month. This appeal is a mandatory step before any court action. The CNAC rules within four months; its decision can then be challenged before the administrative court of appeal.
The following may appeal to the CNAC: the applicant, the prefect, any member of the CDAC, any business operating in the project’s catchment area whose activity is likely to be affected by it, or any association representing them (Article L752-17 of the Commercial Code). The CNAC’s opinion or decision replaces that of the CDAC. The CNAC may also, within one month, take up of its own motion any project with a sales area of 20,000 m² or more.
The one-month period starts at a different point depending on who appeals: notification for the applicant, the committee meeting for the prefect and the members, the latest of the publication formalities for third parties (Article R752-30 of the Commercial Code). An appellant other than the applicant must notify the applicant of the appeal within five days of lodging it with the national committee, failing which the appeal is inadmissible (Article R752-32 of the Commercial Code).
CNAC decisions then go, at first and last instance, to the administrative court of appeal for the area in which the departmental committee sits (Article R311-3 of the Code of Administrative Justice), within two months of notification or publication of the decision (Article R421-1 of the Code of Administrative Justice). The court’s judgment can be appealed on a point of law to the Conseil d’État, France’s highest administrative court.
After a CNAC refusal on the merits, the applicant may file a new application for the same land only if it takes account of the reasons for the refusal. If the new application does not substantially change the project, it may be filed directly with the national committee (Article L752-21 of the Commercial Code, in force since 28 May 2026).
How long does the authorisation last, and what must be done before opening?
With a building permit, the AEC lapses if the sales areas are not open to the public one year after the declaration of completion of the works is filed, and at the latest seven years after the permit became final. Without a permit, it lapses three years after notification.
These periods come from Article R752-20 of the Commercial Code, as amended by Decree No. 2024-1248 of 30 December 2024; they apply to authorisations granted after that decree was published. An action before the administrative courts suspends the lapse period until the final decision.
One last formality comes before opening. One month before the date of opening to the public, the holder sends the prefect, the mayor and the president of the EPCI a certificate of compliance with the authorisation, drawn up at the holder’s expense by a body approved by the prefect. Without a certificate within that time, trading in the space is deemed unlawful (Article L752-23 of the Commercial Code).
What is the risk of trading without authorisation?
The prefect serves formal notice on the operator to close the space traded unlawfully, or to return to the authorised area, within three months. Failing that, the prefect orders closure to the public within fifteen days, backed by a daily penalty (astreinte) of up to €150 per square metre.
The procedure is set out in paragraph II of Article L752-23 of the Commercial Code, cited above:
- authorised officers record the unlawful trading and send their report to the prefect;
- the prefect gives the operator formal notice to close the space concerned, or reduce it to the authorised area, within three months;
- failing that, the prefect issues an order within fifteen days closing it to the public until the situation is actually regularised;
- these measures carry a daily penalty that cannot exceed €150 per square metre traded unlawfully;
- failure to comply with the measures is punishable by a fine of €15,000.
The site owner also has obligations once trading has ended: if the site does not reopen to the public within three years, the owner is responsible for dismantling the buildings and restoring the land (Article L752-1 of the Commercial Code).
How to fit the CDAC into a project timetable
By treating it as an authorisation in its own right, from the feasibility stage. The sales area, the activity and the location set the procedure; the review and appeal periods come on top of those of the permit. No major spending should be committed until the authorisation has been obtained and is no longer open to appeal.
Three checks come before any drawing:
- The planned sales area, store by store and for the retail complex as a whole: the law compares this figure, not the floor area, with the thresholds.
- The location: inside an ORT or not, a municipality with fewer than 20,000 inhabitants, land take or none, vacant retail brownfield sites nearby.
- The brief: a residential building with ground-floor shops, an existing building to convert and a bare site are not subject to the same rules.
A retail brand opening several stores goes through this step on every project: see our guide to property development for a retail brand in six steps. An owner looking first for someone to run their premises should read how to find an operator for a retail unit.
PRIMOE structures projects in Paris and Île-de-France, from feasibility through authorisations to the construction site: this is the PRIMOE Development path. For a project with a retail component, email us at contact@primoe.fr with the planned sales area and the municipality: we will tell you which authorisations to build into the timetable.
In short: prepare for the CDAC before the permit, not after. Sales area, location and brief decide the procedure. Count the review, notification and appeal periods before setting an opening date.
Thresholds, time limits, appeals: common questions about the CDAC
At what sales area is CDAC authorisation required?
Above 1,000 m² of sales area for the creation or extension of a retail store or a retail complex. The threshold is 2,000 m² for a change of trading sector, lowered to 1,000 m² if the new activity is predominantly food, and 2,500 m² for reopening a store that has been closed for three years.
Is an AEC needed on top of the building permit?
No, not as two separate authorisations. When the project needs a building permit, the application is filed at the town hall and the CDAC gives an opinion. If that opinion is favourable, the building permit serves as the retail operating authorisation. If it is unfavourable, the permit cannot be granted.
How long does it take to get a CDAC decision?
Two months from referral to the committee, once the application is complete. If no decision is made within that time, the decision is deemed favourable. The prefect notifies it to the applicant within ten days of the meeting. A one-month period for appeals to the national committee then follows.
Who can challenge a CDAC decision, and within what time?
The applicant, the prefect, the committee members, businesses in the catchment area whose activity may be affected by the project, and the associations that represent them. They have one month to appeal to the national committee (CNAC), which rules within four months. This appeal is mandatory before going to the administrative court of appeal.
How long does a retail operating authorisation remain valid?
For a project with a building permit, the space must open to the public within a year of the declaration of completion of the works being filed, and at the latest seven years after the permit became final. For a project without a permit, the authorisation lapses three years after notification. Court proceedings suspend these periods.
Is the CDAC made up the same way in Paris?
No. In Paris, the committee has five elected officials (the Mayor of Paris, the mayor of the arrondissement where the project is located, an arrondissement councillor, a deputy mayor of Paris and a regional councillor) and three qualified persons. In other departments, it has seven elected officials and four qualified persons. In every case, the prefect chairs it.
Does a residential building with ground-floor shops need CDAC approval?
Only if the sales area exceeds the thresholds. Since 28 May 2026, a development that combines retail and housing in a town centre, within an area covered by a territorial revitalisation operation, is exempt from authorisation where the sales area stays below a quarter of the residential floor area.




