Clients taking on their first project discover a baffling alphabet: MOEX, OPC, AMO, not to mention the design team (maîtrise d’œuvre de conception). Behind these acronyms lie precise, complementary services. Confusing them is costly: either you pay twice for the same service, or no one is responsible at the critical moment.
MOEX, OPC, AMO: the differences at a glance
| MOEX | OPC | AMO | |
|---|---|---|---|
| Role | Direct the execution of the works | Organise the timing of the works | Advise and assist the client |
| Works for | The client, in its dealings with the contractors | The client, across all trade packages | The client only |
| Answers for | Compliance and quality of execution | Keeping to the schedule and the interfaces | Quality of decisions and contracts |
| Typical deliverables | Drawing approvals, site minutes, checked valuations, practical completion | Detailed schedule, progress tracking, rescheduling | Brief, bid analysis, dashboards, alerts |
| When | From site preparation to clearing the snags | From site preparation to handover | From the early stages of the project to handover, or beyond |
What does the MOEX do?
Construction supervision picks up the project where the architect left it: it approves the contractors’ construction drawings, directs the site, checks that what is built complies and takes the project through to practical completion and the clearing of the snags. It is the MOEX that says “this concrete complies” or “this interim valuation can be paid”.
In short: the MOEX answers for the quality and compliance of the execution. Our MOEX service in detail.
What does the OPC do?
Scheduling and coordination organises the site over time: who works when, in what order, with what interfaces between trade packages. The OPC builds the schedule, enforces it and reschedules when something unforeseen happens, measuring the impact on the critical path.
In short: the OPC answers for the schedule. On many projects, MOEX and OPC are given to the same firm, which gives the client a single point of contact for the whole works phase. Our OPC service in detail.
What does the AMO do?
The owner’s representative directs neither the works nor the schedule: it stands on the client’s side. It turns technical issues into clear decisions, analyses contractors’ bids, secures the contracts and checks that everyone keeps their commitments. The AMO is the adviser of the party who pays, in its dealings with everyone else.
In short: the AMO answers for the quality of the client’s decisions. Our AMO service in detail.
What about the other parties on site?
Three other roles are often confused with the above:
- The design team (often the architect) designs the project and produces the design work up to the tender documents. The MOEX then takes over for execution; the two may be carried out by the same firm or by two separate firms.
- The health and safety coordinator (coordonnateur SPS) prevents the risks arising when several contractors work on site at the same time or one after another. Under French law, this coordination is compulsory as soon as several contractors or self-employed workers work on a building site (Article L4532-2 of the Labour Code). It is distinct both from the OPC, which organises timing, and from the MOEX.
- The technical inspector (contrôleur technique) gives opinions on the structural soundness of the building and the safety of people. It inspects, but does not direct the site.
Who declares practical completion?
Neither the MOEX, nor the OPC, nor the AMO: it is the client. Under French law, practical completion (réception) is the act by which the client declares that it accepts the works, with or without snags (Article 1792-6 of the Civil Code). The MOEX assists: it organises the pre-completion inspection, proposes the snags and follows up their clearance. The AMO, if there is one, helps the client make an informed decision.
How to combine them without overlap
The rule is simple: one responsibility, one person responsible. MOEX and OPC can be given to the same firm. AMO, on the other hand, makes most sense when it stays separate: it is the client’s eye on the other services. What must always be written down in black and white is the exact scope of each, in contracts that dovetail without overlapping.
On public contracts in France, the Public Procurement Code lists the elements of a lead consultant’s appointment, including direction of the works contracts and OPC. On private contracts, nothing is imposed: it all comes down to the contract. That is exactly where overlaps and gaps in responsibility appear.
Unsure which set-up suits your project? It is the kind of question that can be settled in one conversation. Write to us.
What other questions come up about MOEX, OPC and AMO?
Six questions come up when a client shares out these services. Each has a short answer; the details are settled in the contracts.
What is the difference between a lead consultant (MOE) and MOEX?
The lead consultant (maître d’œuvre) is the one who designs the project and directs its construction. The MOEX is only the second half: approval of construction drawings, direction of the works, checking valuations, practical completion. When the architect does not oversee the works on site, the MOEX is given to another firm. The details are in our guide Construction supervision (MOEX): tasks and deliverables on a private contract.
What is the difference between OPC and direction of the works contracts (DET)?
They are two separate elements in the list of the French Public Procurement Code: “direction of the execution of works contracts” on the one hand, and “scheduling, management and coordination of the site” on the other (Article R2431-1 of the Public Procurement Code). The first checks what is built and what is paid; the second organises who works, when and in what order.
Is OPC compulsory?
On a private contract, the contract decides: the service exists if the client commissions it. On a public contract, OPC is among the elements that a lead consultant’s appointment may include. In practice, as soon as several contractors follow one another on separate contracts, someone has to hold the overall schedule, and it is better to have that in writing.
MOEX and the contractor’s site manager: is it the same job?
No. The site manager (conducteur de travaux) belongs to the contractor doing the building: they organise its teams, its supplies and its output. The MOEX works for the client: it checks that what the contractor builds complies with the contract and the approved drawings, and that what it invoices matches what has been done.
Can an AMO also act as MOEX?
The two services do not have the same purpose: the MOEX directs the execution, the AMO helps the client decide and check those who execute. If both are given to the same firm, the client loses the independent view that makes the AMO worthwhile. If they are nonetheless combined, the two scopes must be written separately.
Who chooses and pays the MOEX, the OPC and the AMO?
The client, through contracts separate from those of the contractors. These firms work for the client: none of them should be paid by a contractor on the site. To place this item in the budget, see Scheduling and coordination (OPC): how to assess its cost and value.
Download: MOEX, OPC, AMO: who does what on a project (PDF, 6 pages, in French).



