Comparing two OPC bids starts with a simple difficulty: they do not always cover the same work. One provides for drawing up and tracking a master schedule; the other also covers design, procurement, interfaces with the operator and organising the tests. A price on its own does not tell these services apart.
For a private client, the right starting point is how much management the project needs. How many parties have to be coordinated? Which decisions drive the opening date? How much visibility must you keep during the works? The answers let you size the appointment and judge its price on a shared scope.
What does an OPC appointment actually cover?
An OPC appointment covers three tasks: sequencing, which analyses the tasks and sets their order and the critical path; coordination, which aligns the work of the different parties in time and space; and management (pilotage), which puts these measures into practice during the works, until the snags are cleared. On a private contract, the contract sets its extent.
This is the definition the French Public Procurement Code gives for public design and supervision contracts (Article R2431-17 of the Public Procurement Code), where OPC is one of the possible elements of the appointment (Article R2431-1 of the Public Procurement Code). It is not binding on a private project, but it is a useful reference when drafting the contract.
Sequencing is not just lining up bars on a chart: it looks at design, orders, access, the work of each party and the tests. It identifies the sequences where a slip could push back a key deadline.
Coordination resolves situations where two contractors are available on the same day but cannot work together in the same area. Management then tracks the work as it is done, raises the alarm on deviations and prepares the organisational measures to be decided.
On a private contract, tracking design, procurement or snags must be stated expressly in the contract if it is expected. A heading such as “full OPC appointment” is no substitute for that description. The detail of our OPC service shows what we include, step by step.
In short: OPC organises the timing of the works. It sequences the tasks, coordinates the contractors and drives progress until the snags are cleared. No French legal text sets its content on a private contract: what is not written in the contract is not owed.
How does OPC differ from MOEX?
OPC answers for the schedule and the interfaces between trade packages. MOEX (construction supervision) answers for the compliance of the works: it approves the construction documents, runs the site, checks the interim valuations and prepares practical completion. The two roles share their information. They can be given to the same firm, provided each remains identifiable.
If a piece of equipment cannot be ordered because it lacks technical sign-off, MOEX and the specialists deal with the question. OPC measures the consequences of the wait, identifies the latest date for a decision and looks at alternative sequences. The client decides when the choice concerns the brief, cost or time and is the client’s to make.
The fee proposal must therefore set out the joint meetings, the information to be passed on and who is responsible for raising alerts. Nor is OPC the same as health and safety coordination (coordination SPS), which French law requires as soon as several contractors or self-employed workers are working on a building site (Article L4532-2 of the Labour Code). To place each role, see our guide MOEX, OPC, AMO: who does what.
What drives the cost of an OPC appointment?
The cost of an OPC appointment follows the workload, not the floor area of the building. Six factors determine it: the number of trade packages and contractors, the length of the works, the site constraints, the reliability of the design, when the appointment starts and how often a presence on site is required.
- The number of trade packages and parties. Each separate contract adds interfaces to manage: a project let in separate trade packages needs more coordination than a single contract.
- The length of the works. It sets the number of meetings, progress checks and schedule updates.
- The site constraints. A small occupied site can need more day-to-day coordination than a larger building with simple access and repetitive tasks. Working hours, the number of zones and keeping the building in operation weigh directly on the organisation.
- The reliability of the input data. Incomplete design or imprecise contracts mean the assumptions have to be rebuilt before scheduling.
- When the appointment starts. Building a schedule before the works leaves room to act on tendering and procurement. Taking over a site that is already off track first means reconstructing the facts and the commitments: this diagnostic phase is separate from routine monitoring.
- The presence required. One visit a week and a daily presence are not the same appointment. At PRIMOE, a project manager runs three sites at most.
In short: two projects of the same value can call for very different OPC appointments. The price is built from the number of interfaces, the duration, the site constraints and the expected presence. Floor area or the cost of the works, on their own, say nothing about the coordination work.
How is OPC paid: fixed fee, percentage or time basis?
An OPC appointment is paid as a fixed fee, by stage, on a time basis within agreed limits, or as a percentage of the cost of the works. In France there is no official fee scale. The right structure is the one that matches how clearly the scope and the length of the works can be seen.
Scroll the table sideways →
| Fee structure | Suited to cases where | Point to write into the contract |
|---|---|---|
| Overall fixed fee | The scope and length of the works are precisely described | What happens if the works take longer than planned |
| Fixed fee per stage | Preparation, the works and close-out need different resources | The content of each stage and the deliverable that closes it |
| Capped time basis | The appointment starts with a diagnosis or a takeover whose extent is unknown | The cap, the timesheets and the alert threshold |
| Percentage of the cost of the works | The scope is standard and the contract sums are known | The basis used and how variations are treated |
Percentage ranges circulate online. They rest on no official scale and specify neither scope nor presence: they cannot be used to judge a bid. To compare, the client sets side by side the resources offered, the deliverables, the exclusions and the terms for changing the appointment. As a benchmark, PRIMOE’s OPC appointments range from 0.8 to 2% of the cost of the works excl. VAT, depending on the number of contractors, the length of the works and the presence required.
A clear proposal states what happens if the works take longer, if meetings become more frequent or if several recovery scenarios are requested. These terms avoid discovering mid-construction that the management needed goes far beyond what was bought.
How do you compare two OPC bids?
Two OPC bids are compared on the same scope. First set out, in the tender, the tasks expected, the presence and the deliverables; then ask each bidder for the time planned per stage and the name of the person assigned. The price is then read against the resources, not the other way round.
Scroll the table sideways →
| What to compare | Question to ask in the tender |
|---|---|
| Scope | Are design, procurement, tests and snags included? |
| Presence | How often will they visit the site, and how available are they between meetings? |
| Schedule | What level of detail, which zones, and how often will it be updated? |
| Alerts | From what deviation, to whom and with what corrective scenario? |
| Deliverables | Who receives the progress checks, analyses and action plans? |
| Changes on site | How are an extension, a new phasing or a takeover handled? |
- Write the scope before tendering. Construction design, procurement, tests, pre-completion inspections (OPR), clearing the snags: each task is stated as included or excluded.
- Ask about resources. Number of days per stage, the person assigned, how many sites they run at the same time.
- Ask for a sample deliverable. A detailed schedule, site minutes and an alerts table produced on another project tell you more than a brochure.
- Set the rules for change. The price of an extra month, an extra meeting, a recovery scenario.
In short: the cheapest bid is only comparable with the others if it covers the same tasks with the same presence. A price gap between two OPC bids most often reflects a gap in scope or in time spent. That is the gap you need to bring to light.
How do you measure the value of an OPC appointment?
The value of an OPC appointment is measured by three results: the dependencies between trade packages are visible, the contractors’ commitments are dated and in writing, and the client decides early enough for the decision to count. OPC does not remove the unexpected and does not guarantee a date.
A dashboard can track slippage against milestones, blocked tasks, pending decisions and whether short-term commitments are kept. It also shows how the critical path is moving, that is, the sequence of tasks that drives the deadline in question. A pile of completed activities does not make up for a delay on a single critical task.
The cost of delay is worked out project by project. It can include extra finance costs, keeping the site set-up in place for longer and deferred income. You need to separate fixed costs, daily costs and effects triggered when a date is passed, then avoid double counting. This estimate informs decisions; it is not a saving guaranteed by the OPC appointment.
OPC’s records are also useful after the event: contractual dates, recorded delays and the causes noted as the works progress form the material for a delay claim file. See our guide construction delays: proof and penalties.
OPC: the questions clients ask
What does an OPC appointment cost?
In France there is no official fee scale and no price per square metre. At PRIMOE, an OPC appointment ranges from 0.8 to 2% of the cost of the works excl. VAT. The price depends on the number of contractors to coordinate, the length of the works, the site constraints and the presence required. It is expressed as a fixed fee, by stage or on a capped time basis. Ask each bidder for the number of days planned: it is the only reliable basis for comparison.
Is OPC compulsory on a private project?
No. No French legal text requires a private client to appoint OPC. On public contracts, OPC is an element that the lead consultant’s appointment may include. In practice, as soon as a site brings together several contractors on separate trade packages, someone has to run the shared schedule, and the contract had better say who.
Who pays for OPC?
The client, when the appointment is given to a separate firm or to the construction supervisor (MOEX). With a main contractor or a general contractor, coordination of the trades is included in the price of the works contract. Either way, the contract must say who runs the schedule and who reports to the client.
When should OPC be appointed?
Before the works contracts are signed, as soon as the timescales for design, tendering, procurement and works need to be coordinated. Appointed early, the OPC consultant writes the schedule into the contract documents and deals with dependencies before they become emergencies on site. Appointed mid-construction, it starts with a diagnosis.
Do you need OPC with a main contractor?
It depends on the interfaces the client keeps: the operator, equipment the client supplies, work given to third parties, deliveries. If these interfaces exist, a management appointment limited to these points is still useful. The contract must avoid overlap with the organisation already entrusted to the main contractor. See general contractor or separate trade packages.
What are the minimum deliverables to ask for?
A note on how the appointment will be organised, a workable baseline schedule, updates with explanations, written alerts and tracking of the actions decided. Their content and frequency must match the complexity of the project: a schedule updated without commentary does not let you decide anything.
Is OPC liable for every delay?
No. Under French law, its liability is assessed against its obligations, any failures on its part and their consequences (Article 1231-1 of the Civil Code). Delays caused by the contractors, the design or the client’s decisions are analysed separately. OPC must, however, have raised the alarm in time and in writing.
Where do you start when tendering for OPC?
Start by describing the need, not by asking for a price. Four things are enough to go out to tender: the brief, the target date, how the contracts are split and the operating constraints of the site. They let you write a precise management scope, on which the bidders price the same appointment.
PRIMOE provides OPC on its own or together with construction supervision (MOEX), in Paris and Île-de-France. We provide construction supervision on two housing projects: in Pantin (93), in progress, and in Roissy-en-Brie (77), completed. Every meeting is followed by written minutes. To place OPC among all the construction-phase services, see our Delivery path and the guide MOEX: tasks and deliverables. To scope your tender: contact@primoe.fr.